Construction Zone
By Tod Horner
The design and construction staff of
the Facilities and Planning Department has numerous projects at
various stages slated for the summer/fall of 2000. Typically,
we see a peak in construction activities in the summer months and
this summer should be no different. The scheduled projects
vary in size and complexity including building renovations and
additions, parking lot expansions, building system replacements and
construction of a new Physical Therapy building. Project
specifics are as follows:
Ground breaking is scheduled for
April for the new multi-million dollar state of the art Physical Therapy Building. The 41,000
square foot, three story, block and brick building will be located
between Vincent Science Hall and Spotts World Culture facing Bailey
Library. Physical Therapy faculty offices, classrooms, smart
classrooms, research labs and cadaver labs will be housed in the
new building. The building will also feature multi-level
entrances. Construction is scheduled to be completed by
summer of 2001.
The Heating Plant renovation project is currently
under way. Contractors are mobilizing and working on the
required submittals. This is the first phase of a two phase
project. Phase I includes the installation of additional gas
firing to the existing coal fired boilers #1 and #2 and is
scheduled to be completed in July. The above work is
necessary because of citations issued by the Department of
Environmental Protection for stack emissions violations.
Design of Phase II will immediately follow the completion of Phase
I and will include a new stack, conversion of boiler #3 to gas,
coal handling improvements and demolition of the existing coal
silo.
The badly deteriorated heating
system in Bard Hall is scheduled to
be replaced this summer with a new four pipe heating and cooling
system. This project will also be done in two phases May to
September 2000 and May to September 2001.
With the completion of the campus
wide master plan, North Hall will become a "one stop shop" for
students needing assistance from various departments in numerous
buildings. The first step is to relocate the Health Services
Department. The first floor of the east/west wing of Rhoads Hall was chosen as the best location.
Design is nearing completion and construction should start in
September. The space will be developed into a more
department-oriented facility than that is currently being used by
Health Services. Construction is scheduled to be completed in April
2001.
According to the dining services
people Rocky's Grill has become a
popular social center for students. Design of 2500 square foot (176
seating) single story addition is nearly completed. An exterior
wood deck will also be included. he addition will face the new
Recreation Facility and Swope Music Hall. Construction is
scheduled to start in July and proceed into late fall.
The Department of General Services
is coordinating a project for the renovation of West Hall. Built
around 1900, West Hall has had
limited work performed to it other than a new roof in 1993. Offices
of International Initiatives and Modern Languages offices and
classrooms are slated to occupy the building. The project includes
a new elevator, new electrical/plumbing/hvac systems, new windows
and a new main entrance facing Maltby avenue. Construction is
scheduled to start January 2001.
The bleacher system in Morrow Field House has been a maintenance
problem for many years. Proposals for the bleacher replacement,
including additional seating, are now being accepted. After the
existing bleachers are removed, the arena wood floor will also be
replaced. Both systems are from the original building construction
of the 1960's. In addition, the outlining "grass-tex" area is
being considered for replacement. All work will start immediately
following spring commencement, and finish in the early
fall. A fast track design is underway for repairs and
renovations to the Spotts World
Culture elevated Walkway. Due to many years of exposure
to the elements, the walkway deck is badly deteriorated and the
structure is experiencing some movement. The concrete steps will be
replaced, the deck will be repaired and the stability of the
structural supports will be reviewed. A new cover will also be
added to protect the walkway from the weather and improve
pedestrian use. The work is tentatively scheduled to start July and
finish sometime in the fall.
A considerable amount of work is
being planned as part of the ongoing multiple year asphalt maintenance contract. The baseball
field parking will be expanded and reconfigured. Founders Hall
parking lot will be resurfaced. The existing tennis courts at
Founders will be converted to a parking lot.The Swope parking lot
will be expanded to connect with the new lot created when the
Aebersold Recreation Facility was built. Paving will start with
good weather conditions and continue through the paving
season.
As you can see this summer's
construction season will be very busy. Hopefully most of the above
mentioned work will be performed with minimal disruption to the
campus community.
|
What's
Happening Around Campus??
By Lori Wolfe
The Facilities and Planning Crews have been busy working on
the following projects over the past several months:
-Renovation of Head Start Building
to New Martha Gault Art Gallery
-Renovation of Basement of Vincent
House for New Classroom for Counsel/Ed Psychology
-Completed 117G Office Complex at
Vincent Science Hall.
-Rock Lab--Room 210A/B--Vincent
Science Hall
-Safety Modifications to Pool
Bleachers--Morrow Field House
-Bus Shelters--Weisenfluh & Rock
Apartments
-Construct New Office--Purchasing
Department, Old Main.
-Renovate Printing Services Area at
Stores Building
Safety Zone
By Deb Vogan
Are you aware of the rule of thumb
for back flexion? When an individual attempts to lift a heavy
object, not only are they picking up the weight of the object but
also 60% of their own body weight.
For Example:
Object weight = 40lbs.
Individual's weight =
125lbs.
125 x 60% = 75lbs. + 40 lbs. =
115lbs.
Using a back belt does not increase your muscle strength. The
belt does not make you stronger. The above safety tips can be
applied to all of Facilities Crews. For additional
information on proper lifting techniques and back belt usage,
contact Bill Rudloff or Ron Steele.
Using proper lift techniques will
help prevent back injuries.
-Bend at the Knees
-Lift with your legs not your
back
-Keep back straight and in its
normal S curve
-Utilize handles to improve
grip
-Do not twist at completion of a
lift, step and turn
Good Luck and Be Safety
Conscious
The Safety Zone column will appear
in every newsletter. If you have a specific topic that you
would like to see addressed in this column, please contact the
newsletter committee.
Did You
Know That.......
|